← Back to map

Springbok 3 Solar Farm Hybrid

Kern County, California · EIA plant ID 60491 · Operator: 64KT 8me LLC
SolarBatteriesSolar PhotovoltaicBA: LDWP
Nameplate92MWSummer 92 MW
Generators2in service
Net generation225GWh12 mo to Aug 2026
Capacity factor29%solar units, summer MW
Heat rate—thermal plants only
First online2019

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0102030GWh2020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20192020202120222023202420252026202728.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2019112.628.3%—
2020242.630.7%—
2021238.730.3%—
2022234.229.7%—
2023233.929.7%—
2024246.731.2%—
2025251.131.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
SB3BSBatteriesBA1.51.5Jul 2019Operating—coming soon
SB3SFSolar PhotovoltaicPV9090Jul 2019Operating—coming soon

Owner / operator

Operator: 64KT 8me LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
64KT 8me LLC100.0%92 MW

Nearby plants

Within 80 km.
California City2 MW2.4 km
CalCity Solar 13 MW4.6 km
Eland Solar & Storage Center, Phase 2 Hy458 MW5.5 km
Eland Solar & Storage Center, Phase 1 Hy460 MW6.3 km
RE Barren Ridge 160 MW7.1 km
Springbok Solar Farm 2155 MW9.1 km