Eland Solar & Storage Center, Phase 2 Hy

Kern County, California · EIA plant ID 61169 · Operator: 69SV 8me LLC
SolarBatteriesSolar PhotovoltaicBA: LDWP
Nameplate458MWSummer 350 MW
Generators2in service
Net generation668GWh12 mo to Aug 2026
Capacity factor39%solar units, summer MW
Heat rate—thermal plants only
First online2025

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
020406080GWh2026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%20252026202739.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2025260.130.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
61169BatteriesBA150150Jul 2025Operating—coming soon
69SV8Solar PhotovoltaicPV308200Jul 2025Operating—coming soon

Owner / operator

Operator: 69SV 8me LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Arevon Asset Management100.0%458 MW

Nearby plants

Within 80 km.
Eland Solar & Storage Center, Phase 1 Hy460 MW0.8 km
Springbok Solar Farm 2155 MW3.7 km
Springbok Solar Farm 1105 MW4.1 km
Hecate Energy Beacon Solar 356 MW5.3 km
Springbok 3 Solar Farm Hybrid92 MW5.5 km
Beacon Solar Plant Site 247 MW5.8 km