← Back to map

Springbok Solar Farm 2

Kern County, California · EIA plant ID 59840 · Operator: 63SU 8me, LLC
SolarSolar PhotovoltaicBA: LDWP
Nameplate155MWSummer 155 MW
Generators1in service
Net generation397GWh12 mo to Dec 2025
Capacity factor29%solar units, summer MW
Heat rate—thermal plants only
First online2016

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02040GWh201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20162018202020222024202629.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201679.217.4%—
2017417.630.8%—
201840730.0%—
2019408.730.1%—
202041130.2%—
2021415.530.6%—
2022427.731.5%—
2023404.229.8%—
202439929.3%—
2025397.129.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
SB2Solar PhotovoltaicPV155155Sep 2016Operating—coming soon

Owner / operator

Operator: 63SU 8me, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
63SU 8me, LLC100.0%155 MW

Nearby plants

Within 80 km.
Springbok Solar Farm 1105 MW2 km
Beacon Solar Plant Site 247 MW2.7 km
Eland Solar & Storage Center, Phase 1 Hy460 MW2.9 km
Hecate Energy Beacon Solar 356 MW3.5 km
Eland Solar & Storage Center, Phase 2 Hy458 MW3.7 km
Hecate Energy Beacon Solar 156 MW4 km