Jicarilla Solar 2
Rio Arriba County, New Mexico · EIA plant ID 65103 · Operator: Repsol Renewables NA
Nameplate50MWSummer 50 MW
Generators1in service
Net generation130GWh12 mo to Aug 2026
Capacity factor30%solar units, summer MW
Heat rate—thermal plants only
First online2023
The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2022 | 108.6 | — | — |
| 2023 | 132.5 | 40.2% | — |
| 2024 | 118.6 | 27.0% | — |
| 2025 | 127.6 | 29.1% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| JICS2 | Solar Photovoltaic | PV | 50 | 50 | Apr 2023 | Operating | — | coming soon |
Owner / operator
Operator: Repsol Renewables NA. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Repsol Renewables NA | 100.0% | 50 MW |
Nearby plants
Within 80 km.
| Shallow Basket | 190 MW | 17.6 km |
| Jicarilla Solar 1 LLC | 70 MW | 21.7 km |
| Cuba 2.5ac, LLC | 3 MW | 24.5 km |
| Arroyo Solar Energy Storage Hybrid | 450 MW | 40 km |
| El Vado Dam | 8 MW | 63.8 km |
| Abiquiu Dam | 16 MW | 68 km |