North Lancaster Ranch

Los Angeles County, California · EIA plant ID 59962 · Operator: AES Distributed Energy
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate20MWSummer 18 MW
Generators1in service
Net generation39GWh12 mo to Dec 2025
Capacity factor24%solar units, summer MW
Heat rate—thermal plants only
First online2016

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
01234GWh201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20162018202020222024202624.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201616.5%—
201739.522.6%—
201838.624.4%—
201938.924.7%—
202033.721.3%—
202135.222.3%—
20222817.8%—
202328.918.3%—
202437.223.6%—
202538.624.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
NLRSolar PhotovoltaicPV2018Dec 2016Operating—coming soon

Owner / operator

Operator: AES Distributed Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
North Lancaster Ranch100.0%20 MW

Nearby plants

Within 80 km.
Summer Solar LLC20 MW0.6 km
Antelope Expansion 3B5 MW0.9 km
Central Antelope Dry Ranch C20 MW1.2 km
Antelope Expansion 3A15 MW1.3 km
Western Antelope Blue Sky B20 MW1.4 km
TA-High Desert LLC20 MW1.4 km