Scholl CanyonUnder construction
Los Angeles County, California · EIA plant ID 69749 · Operator: City of Glendale - (CA)
12 MW under construction (Landfill Gas), first expected Feb 2027 · EIA-860M
Nameplate—MWSummer — MW
Generators0in service · 12 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—
Capacity factor by year
Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| U1 | Landfill Gas | IC | 3 | 2.8 | planned Feb 2027 | Under construction | — | coming soon |
| U2 | Landfill Gas | IC | 3 | 2.8 | planned Feb 2027 | Under construction | — | coming soon |
| U3 | Landfill Gas | IC | 3 | 2.8 | planned Feb 2027 | Under construction | — | coming soon |
| U4 | Landfill Gas | IC | 3 | 2.8 | planned Feb 2027 | Under construction | — | coming soon |
Owner / operator
Operator: City of Glendale - (CA). Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Nearby plants
Within 80 km.
| Occidental College Solar Project | 1 MW | 3.4 km |
| Glenarm | 266 MW | 5.2 km |
| Glenarm BESS Plant | — | 5.3 km |
| CalTech - Pasadena Wilson Ave | 2 MW | 6.3 km |
| California Institute of Technology | 13 MW | 6.5 km |
| Caltech Central | 1 MW | 6.5 km |