← Back to map

Bishop Ranch - BR 3-HHUnder construction

Contra Costa County, California · EIA plant ID 69708 · Operator: Camino Ramon BR 3-HH Solar Project 2020, LLC
SolarCAISOBA: CISO

1 MW under construction (Batteries, Solar Photovoltaic), first expected Jul 2027 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 1 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
4150BBatteriesBA0.60.6planned Jul 2027Under construction—coming soon
4150CSolar PhotovoltaicPV0.60.6planned Jul 2027Under construction—coming soon
4150RSolar PhotovoltaicPV0.20.2planned Jul 2027Under construction—coming soon

Owner / operator

Operator: Camino Ramon BR 3-HH Solar Project 2020, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Bishop Ranch - BR 3-GG—0.1 km
Bishop Ranch - BR 3-FF—0.2 km
Bishop Ranch - BR 26003 MW0.3 km
Bishop Ranch - BR 1-Y2 MW0.5 km
Bishop Ranch - BR 15-DD1 MW0.7 km
Bishop Ranch BR 1-X1 MW0.8 km