← Back to map

Bishop Ranch BR 1-X

Contra Costa County, California · EIA plant ID 67743 · Operator: Bollinger Canyon Road BR 1-X Solar Project 2020
SolarBatteriesSolar PhotovoltaicCAISOBA: CISO
Nameplate1MWSummer 1 MW
Generators3in service
Net generation2GWh12 mo to Dec 2025
Capacity factor19%solar units, summer MW
Heat rate—thermal plants only
First online2022

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
050100150200MWh20242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20242025202619.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20241.620.1%—
20251.519.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
4057BBatteriesBA0.50.5Mar 2022Operating—coming soon
4057CSolar PhotovoltaicPV0.60.6Mar 2022Operating—coming soon
4057RSolar PhotovoltaicPV0.30.3Mar 2022Operating—coming soon

Owner / operator

Operator: Bollinger Canyon Road BR 1-X Solar Project 2020. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Bollinger Canyon Road BR 1-X Solar Project 2020100.0%1 MW

Nearby plants

Within 80 km.
Bishop Ranch - BR 1-Y2 MW0.3 km
Bishop Ranch - BR 3-HH—0.8 km
Bishop Ranch - BR 3-GG—0.9 km
Bishop Ranch - BR 26003 MW0.9 km
Bishop Ranch - BR 3-FF—1 km
Bishop Ranch - BR 8-P2 MW1.3 km