San Miguel County, New Mexico · EIA plant ID 69529 · Operator: Standard Solar
SolarSolar PhotovoltaicBA: PNM
Nameplate5MWSummer 5 MW
Generators1in service
Net generation1GWh12 mo to Dec 2025
Capacity factor8%solar units, summer MW
Heat rate—thermal plants only
First online2025

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600MWh2025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%3%5%8%202520268.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20250.68.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PINOSolar PhotovoltaicPV55Nov 2025Operating—coming soon

Owner / operator

Operator: Standard Solar. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Standard Solar100.0%5 MW

Nearby plants

Within 80 km.
Las Vegas Solar Energy Center5 MW2.3 km
San Miguel I Solar Energy Center10 MW4.5 km
Storrie Lake Solar Project2 MW4.9 km
San Miguel II Solar Energy Center10 MW5 km
Juniper Sol Solar CSG5 MW66.9 km
Santa Fe Solar Energy Center10 MW75.4 km