← Back to map

Kearsarge William Way

Norfolk County, Massachusetts · EIA plant ID 64617 · Operator: Kearsarge William Way LLC
SolarBatteriesSolar PhotovoltaicISONEBA: ISNE
Nameplate7MWSummer 7 MW
Generators2in service
Net generation7GWh12 mo to Dec 2025
Capacity factor20%solar units, summer MW
Heat rate—thermal plants only
First online2021

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600800MWh2022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20212022202320242025202619.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20210.12.9%—
20227.520.2%—
20237.219.4%—
20247.419.8%—
20257.319.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BWBATBatteriesBA2.62.6Dec 2021Operating—coming soon
BWWSolar PhotovoltaicPV4.44.4Dec 2021Operating—coming soon

Owner / operator

Operator: Kearsarge William Way LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Kearsarge William Way LLC100.0%7 MW

Nearby plants

Within 80 km.
Bellingham Cogeneration Facility386 MW1.4 km
Mendon3 MW1.9 km
BWC Muddy Brook, LLC Hybrid2 MW2 km
BWC Wading River One, Two, Three CSG3 MW2.8 km
Kearsarge Bellingham PV3 MW3 km
ANP Blackstone Energy Project578 MW3.1 km