Polk County, Florida · EIA plant ID 60124 · Operator: goldfinch (lakeland)
SolarSolar PhotovoltaicBA: FMPP
Nameplate3MWSummer 3 MW
Generators1in service
Net generation5GWh12 mo to Dec 2025
Capacity factor18%solar units, summer MW
Heat rate—thermal plants only
First online2016

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600MWh201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20162018202020222024202618.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20160.15.0%—
20175.721.7%—
20185.119.4%—
20195.219.8%—
2020622.7%—
20215.721.6%—
20222.59.4%—
20232.28.5%—
20244.416.9%—
20254.818.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GFNCHSolar PhotovoltaicPV33Dec 2016Operating—coming soon

Owner / operator

Operator: goldfinch (lakeland). Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
goldfinch (lakeland)100.0%3 MW

Nearby plants

Within 80 km.
Lakeland Electric Co. (FL)-Airport 12 MW0.9 km
Lakeland Electric Co. (FL) - Airport II4 MW1.1 km
English Creek Solar23 MW4.7 km
Winston50 MW5.6 km
Laurel Oaks Solar61 MW6.6 km
Magnolia Solar75 MW7.2 km