← Back to map

Five Points Solar Park

Fresno County, California · EIA plant ID 59523 · Operator: Boralex US Operations LLC
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate60MWSummer 60 MW
Generators1in service
Net generation81GWh12 mo to Dec 2025
Capacity factor15%solar units, summer MW
Heat rate—thermal plants only
First online2016

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
051015GWh201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20162018202020222024202615.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201642.924.4%—
201714928.3%—
2018162.130.9%—
2019144.527.5%—
2020134.725.6%—
2021141.827.0%—
2022139.226.5%—
202310219.4%—
202493.317.7%—
202580.715.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
FRFSPSolar PhotovoltaicPV6060Sep 2016Operating—coming soon

Owner / operator

Operator: Boralex US Operations LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Boralex Five Points Holdings LLC50.0%30 MW
GSPPR LLC50.0%30 MW

Nearby plants

Within 80 km.
Darden II Solar—7.9 km
Whitney Point Solar20 MW8.9 km
NextEra Westside PV20 MW9.2 km
Darden IV Solar—9.7 km
Westside Solar Station15 MW10 km
Cantua Solar Station20 MW10.5 km