← Back to map

Westside Solar Station

Fresno County, California · EIA plant ID 57499 · Operator: Pacific Gas & Electric Co
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate15MWSummer 15 MW
Generators1in service
Net generation12GWh12 mo to Dec 2025
Capacity factor9%solar units, summer MW
Heat rate—thermal plants only
First online2011

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
024GWh201120122013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%201220142016201820202022202420269.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20118.315.2%—
201232.324.5%—
201332.624.8%—
201432.124.4%—
201528.721.9%—
201630.623.2%—
201725.419.3%—
201828.721.9%—
201927.721.1%—
202024.418.5%—
202120.815.9%—
202217.713.5%—
202318.514.1%—
202413.910.5%—
2025129.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV1515Aug 2011Operating—coming soon

Owner / operator

Operator: Pacific Gas & Electric Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Pacific Gas & Electric Co100.0%15 MW

Nearby plants

Within 80 km.
NextEra Westside PV20 MW0.9 km
Whitney Point Solar20 MW1.2 km
Five Points Solar Station15 MW3.1 km
Five Points Solar Park60 MW10 km
Darden IV Solar—11 km
Open Sky Dairy2 MW12.4 km