Nameplate200MWSummer 200 MW
Generators1in service
Net generation626GWh12 mo to Aug 2026
Capacity factor36%wind units, summer MW
Heat rate—thermal plants only
First online2015

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
020406080GWh20162017201820192020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%20162018202020222024202635.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2015256.734.9%—
2016709.440.4%—
2017655.737.4%—
2018683.339.0%—
2019677.238.6%—
2020677.938.6%—
2021650.437.1%—
2022638.936.4%—
2023625.835.7%—
2024589.133.5%—
202560434.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Onshore Wind TurbineWT200.1200.1Aug 2015Operating—siemens SWT-2.3-108

Owner / operator

Operator: Pattern Operators LP. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Logans Gap Wind LLC100.0%200 MW

Nearby plants

Within 80 km.
Flat Top Wind I200 MW17.4 km
Zephyr Storage—20.3 km
Darkwood Solar—27.8 km
Chisme Solar and Storage—30.8 km
Priddy Wind Project302 MW35.7 km
Grizzly Ridge Solar100 MW46 km