← Back to map

Priddy Wind Project

Mills County, Texas · EIA plant ID 64165 · Operator: Engie North America
WindOnshore Wind TurbineERCOTBA: ERCO
Nameplate302MWSummer 302 MW
Generators1in service
Net generation1,024GWh12 mo to Aug 2026
Capacity factor39%wind units, summer MW
Heat rate—thermal plants only
First online2022

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0255075100GWh20222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20222023202420252026202738.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2022850.932.1%—
2023948.335.8%—
2024958.636.1%—
20251,014.938.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
WTG1Onshore Wind TurbineWT302.4302.4Jan 2022Operating—nordex N149/4.0-4.5

Owner / operator

Operator: Engie North America. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Engie North America100.0%302 MW

Nearby plants

Within 80 km.
Flat Top Wind I200 MW18.3 km
Goldthwaite Wind Energy Facility150 MW18.5 km
Castle Gap Wind197 MW21.4 km
Chisme Solar and Storage—31.1 km
Grizzly Ridge Solar100 MW34 km
Logans Gap Wind LLC200 MW35.7 km