← Back to map

Imperial Solar Energy Center West

Imperial County, California · EIA plant ID 57491 · Operator: CSOLAR IV West LLC
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate149MWSummer 149 MW
Generators1in service
Net generation357GWh12 mo to Dec 2025
Capacity factor27%solar units, summer MW
Heat rate—thermal plants only
First online2016

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
010203040GWh201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20162018202020222024202627.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2016315.332.1%—
2017390.630.0%—
2018377.329.0%—
2019394.930.3%—
202039029.9%—
2021401.330.8%—
202242832.9%—
2023388.329.8%—
2024373.628.6%—
202535727.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
56819Solar PhotovoltaicPV148.7148.7Apr 2016Operating—coming soon

Owner / operator

Operator: CSOLAR IV West LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Tenaska CSOLAR West Holdings, LLC74.0%110 MW
CD Global Solar II, CSOLAR, LLC25.0%37 MW
Tenaska CSOLAR West, LLC1.0%2 MW

Nearby plants

Within 80 km.
SEPV Imperial Dixieland East2 MW2.3 km
SEPV Imperial Dixieland West3 MW2.4 km
Kingsley Solar Farm—5.3 km
Campo Verde Solar147 MW5.4 km
Centinela State Prison6 MW6 km
CED West Side Canal Battery Storage131 MW7.4 km