Caledonia

Lowndes County, Mississippi · EIA plant ID 55197 · Operator: Tennessee Valley Authority
Natural gasNatural Gas Fired Combined CycleBA: TVA
Nameplate801MWSummer 765 MW
Generators6in service
Net generation4,764GWh12 mo to Aug 2026
Capacity factor71%gas/coal/oil units, summer MW
Heat rate6,966Btu/kWhfossil units, electric fuel, HHV
First online2003Runs as baseload

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400GWh200420062008201020122014201620182020202220242026

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%2005201020152020202571.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
6,0007,0008,0009,000200520102015202020256,966 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2003446.611.1%8,997
20041,389.220.2%7,129
20051,076.615.7%7,104
2006949.513.8%6,944
20072,096.532.2%7,069
20082,65739.5%6,972
20093,627.854.1%6,885
20104,164.962.2%7,153
20113,72955.6%7,293
20124,510.567.1%7,341
20133,277.248.9%7,288
20142,717.840.6%7,248
20153,413.550.9%7,243
20164,773.471.0%7,242
20174,340.864.8%7,153
20184,064.360.7%7,046
20193,958.159.1%6,925
20204,515.367.2%6,892
20214,36065.1%6,932
20224,662.469.6%6,925
20233,897.858.2%6,969
20245,125.576.3%6,982
20255,246.978.3%6,988

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CTG1Natural Gas Fired Combined CycleCT161157Jun 2003Operating—coming soon
CTG2Natural Gas Fired Combined CycleCT161157Jun 2003Operating—coming soon
CTG3Natural Gas Fired Combined CycleCT161157Jun 2003Operating—coming soon
STG1Natural Gas Fired Combined CycleCA10698Jun 2003Operating—coming soon
STG2Natural Gas Fired Combined CycleCA10698Jun 2003Operating—coming soon
STG3Natural Gas Fired Combined CycleCA10698Jun 2003Operating—coming soon

Owner / operator

Operator: Tennessee Valley Authority. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
GE Energy Financial Services100.0%801 MW

Nearby plants

Within 80 km.
New Caledonia—4 km
Optimist250 MW29.8 km
Columbus MS129 MW36.3 km
Golden Triangle250 MW40.9 km
Golden Triangle II200 MW41.4 km
SR Sipsey—42.3 km