Douglas County, Oregon · EIA plant ID 3029 · Operator: PacifiCorp
HydroConventional HydroelectricBA: PACW
Nameplate32MWSummer 32 MW
Generators1in service
Net generation120GWh12 mo to Dec 2025
Capacity factor43%hydro units, summer MW
Heat rate—thermal plants only
First online1955

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
051015GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%2005201020152020202542.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2001103.542.2%—
2002113.846.4%—
200380.632.9%—
2004141.257.4%—
2005101.339.9%—
200615059.1%—
2007127.545.5%—
2008148.652.9%—
2009127.545.5%—
2010111.439.7%—
2011168.260.0%—
2012166.559.3%—
2013123.944.2%—
2014140.950.2%—
2015123.644.1%—
2016134.147.7%—
2017174.962.4%—
2018124.944.5%—
2019114.540.8%—
202082.829.4%—
202183.329.7%—
2022104.137.1%—
202388.531.6%—
2024105.237.4%—
2025120.142.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY3232Jul 1955Operating—coming soon

Owner / operator

Operator: PacifiCorp. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
PacifiCorp100.0%32 MW

Nearby plants

Within 80 km.
Clearwater 115 MW13.7 km
Lemolo 244 MW14.9 km
Clearwater 226 MW16.3 km
Toketee Falls43 MW18.5 km
Fish Creek11 MW18.5 km
Slide Creek18 MW19.3 km