← Back to map

Iron BESSUnder construction

Fresno County, California · EIA plant ID 68924 · Operator: Panoche BESS LLC
BatteryCAISOBA: CISO

60 MW under construction (Batteries), first expected Apr 2027 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 60 MW building
Net generation—GWh12 mo
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
IROBBatteriesBA59.557planned Apr 2027Under construction—coming soon

Owner / operator

Operator: Panoche BESS LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Midway BESS—0 km
Panoche Peaker57 MW0.1 km
Midway Peaking LLC140 MW0.2 km
CalPeak Power Panoche Peaker Plant61 MW0.2 km
Panoche Energy Center432 MW0.5 km
Conflitti Solar4 MW2.8 km