Sunstone SolarPlanned
Morrow County, Oregon · EIA plant ID 68396 · Operator: Sunstone Solar, LLC
2,400 MW planned (Batteries, Solar Photovoltaic), first expected Dec 2027 · EIA-860M
Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online—
Capacity factor by year
Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| PGB45 | Batteries | BA | 1,200 | 1,200 | planned Dec 2027 | Planned | — | coming soon |
| PGR45 | Solar Photovoltaic | PV | 1,200 | 1,200 | planned Dec 2027 | Planned | — | coming soon |
Owner / operator
Operator: Sunstone Solar, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Nearby plants
Within 80 km.
| Wheatridge Optimization I | — | 6.9 km |
| Wheatridge Optimization II | — | 7.3 km |
| Wheatridge Hybrid | 280 MW | 7.5 km |
| Wheatridge 1 | 100 MW | 7.5 km |
| Sand Ranch Windfarm LLC | 10 MW | 8 km |
| Pacific Canyon Windfarm LLC | 8 MW | 8 km |