Bluebonnet Prairie WindUnder construction

Navarro County, Texas · EIA plant ID 68082 · Operator: Leeward Asset Management, LLC
WindERCOTBA: ERCO

170 MW under construction (Onshore Wind Turbine), first expected Dec 2027 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 170 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BBPOnshore Wind TurbineWT170170planned Dec 2027Under construction—coming soon

Owner / operator

Operator: Leeward Asset Management, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Elm Flats Solar—3.4 km
Gaia Hybrid230 MW10.1 km
Fence Post Solar Hybrid Project, LLC308 MW10.7 km
WAL5651 MW10.8 km
Armadillo Solar Center—18.5 km
Wensowitch Solar Park—18.6 km