← Back to map

Harmony Florida Solar II

Osceola County, Florida · EIA plant ID 67208 · Operator: Harmony Florida Solar II, LLC
SolarSolar PhotovoltaicBA: FPC
Nameplate75MWSummer 75 MW
Generators1in service
Net generation185GWh12 mo to Aug 2026
Capacity factor28%solar units, summer MW
Heat rate—thermal plants only
First online2024

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
05101520GWh20252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%202420252026202728.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202412.923.4%—
2025184.228.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
HARSSolar PhotovoltaicPV74.574.5Dec 2024Operating—coming soon

Owner / operator

Operator: Harmony Florida Solar II, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Harmony Florida Solar II, LLC100.0%75 MW

Nearby plants

Within 80 km.
Harmony Solar75 MW2.7 km
Osceola580 MW4.4 km
JED Solid Waste Mgmt Renewable Energy10 MW11.6 km
Storey Bend Solar75 MW12.9 km
Turnpike Solar Plant—17.8 km
Lonesome Camp Solar Plant—18.2 km