← Back to map

Bird Dog Solar

Burke County, Georgia · EIA plant ID 66024 · Operator: Bird Dog Solar, LLC
SolarSolar PhotovoltaicBA: SOCO
Nameplate40MWSummer 40 MW
Generators1in service
Net generation98GWh12 mo to Aug 2026
Capacity factor28%solar units, summer MW
Heat rate—thermal plants only
First online2023

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02.557.510GWh202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2023202420252026202727.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20233.511.8%—
202490.325.7%—
202597.127.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GA-01Solar PhotovoltaicPV4040Dec 2023Operating—coming soon

Owner / operator

Operator: Bird Dog Solar, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Bird Dog Solar, LLC100.0%40 MW

Nearby plants

Within 80 km.
Shawnee - GA2 MW2.7 km
White Oak Solar, LLC77 MW14.4 km
Cabokenze Energy Storage—14.9 km
Waynesboro Community Solar2 MW17.1 km
Vogtle4,658 MW22.1 km
Hobnail Solar70 MW22.4 km