Okaloosa County, Florida · EIA plant ID 65888 · Operator: Florida Power & Light Co
BatteryBatteriesSolar PhotovoltaicBA: FPL
Nameplate149MWSummer 149 MW
Generators2in service
Net generation164GWh12 mo to Aug 2026
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online2024

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
05101520GWh20252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202414.2——
2025181.1——

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV74.574.5Dec 2024Operating—coming soon
2BatteriesBA74.574.5Dec 2025Operating—coming soon

Owner / operator

Operator: Florida Power & Light Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Florida Power & Light Co100.0%149 MW

Nearby plants

Within 80 km.
Gulf Coast Solar Center I30 MW14.4 km
Canoe149 MW45.1 km
Gulf Coast Solar Center II40 MW45.3 km
Big Juniper Solar75 MW54.2 km
Chautauqua Solar Energy Center75 MW55.2 km