← Back to map

Gulf Coast Solar Center II

Santa Rosa County, Florida · EIA plant ID 59690 · Operator: CD Arevon USA, Inc.
SolarSolar PhotovoltaicBA: SOCO
Nameplate40MWSummer 40 MW
Generators1in service
Net generation82GWh12 mo to Aug 2026
Capacity factor23%solar units, summer MW
Heat rate—thermal plants only
First online2017

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02468GWh201820192020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2018202020222024202623.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201711.119.0%—
201877.222.0%—
201978.622.4%—
202081.423.2%—
202178.422.4%—
202265.418.6%—
202377.622.1%—
202479.522.6%—
202578.822.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GCSC2Solar PhotovoltaicPV4040Nov 2017Operating—coming soon

Owner / operator

Operator: CD Arevon USA, Inc.. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
CD Arevon USA, Inc.100.0%40 MW

Nearby plants

Within 80 km.
Big Juniper Solar75 MW23.4 km
Blackwater River Solar Energy Center149 MW24.4 km
Santa Rosa Energy Center275 MW25.9 km
Pea Ridge14 MW29.2 km
Canoe149 MW29.8 km
Standby Generation Plant14 MW33 km