← Back to map

Winfield

Putnam County, West Virginia · EIA plant ID 6562 · Operator: Appalachian Power Co
HydroConventional HydroelectricPJMBA: PJM
Nameplate25MWSummer 19 MW
Generators3in service
Net generation93GWh12 mo to Dec 2025
Capacity factor57%hydro units, summer MW
Heat rate—thermal plants only
First online1938

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
051015GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%50%100%150%2005201020152020202556.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200194.866.0%—
2002101.970.9%—
2003133.893.2%—
2004134.293.2%—
2005111.4142.9%—
200699.6127.7%—
200791.4117.3%—
200894.9121.4%—
2009126.8162.6%—
20109658.6%—
201182.350.3%—
2012102.162.2%—
201396.558.9%—
201416.610.1%—
201583.450.9%—
201610865.7%—
201780.749.2%—
201866.540.6%—
201984.251.4%—
2020101.862.0%—
2021104.463.7%—
2022125.876.8%—
2023110.567.5%—
202484.451.4%—
20259356.8%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY14.78.9Jan 1938Operating—coming soon
2Conventional HydroelectricHY4.94.9Jan 1938Operating—coming soon
3Conventional HydroelectricHY4.94.9Jan 1938Operating—coming soon

Owner / operator

Operator: Appalachian Power Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Appalachian Power Co100.0%25 MW

Nearby plants

Within 80 km.
John E Amos2,933 MW9.9 km
AEP Milton NaSretired26 km
R.C. Byrd L&D Hydroelectric Project—28.6 km
Marmet14 MW42.8 km
Racine47 MW43.1 km
BHER Ravenswood Solar 1192 MW43.7 km