Broadway 3 - UC Merced 1
Merced County, California · EIA plant ID 65186 · Operator: GSRP
Nameplate1MWSummer 1 MW
Generators1in service
Net generation1GWh12 mo to Dec 2025
Capacity factor11%solar units, summer MW
Heat rate—thermal plants only
First online2009
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2021 | 1 | 11.7% | — |
| 2022 | 1.8 | 20.2% | — |
| 2023 | 1.2 | 13.9% | — |
| 2024 | 0.9 | 10.3% | — |
| 2025 | 0.9 | 10.6% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| GEN1 | Solar Photovoltaic | PV | 1 | 1 | Oct 2009 | Operating | — | coming soon |
Owner / operator
Operator: GSRP. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Wells Fargo Equipment Finance Inc | 100.0% | 1 MW |
Nearby plants
Within 80 km.
| UC Merced Solar Hybrid | 5 MW | 0.2 km |
| 2097 Helton Solar Project | 2 MW | 6.8 km |
| Mission Solar LLC | 2 MW | 11.7 km |
| Merced Solar LLC | 2 MW | 11.7 km |
| Parker | 3 MW | 12.7 km |
| Merced Pipeline | 4 MW | 17.7 km |