← Back to map

Kings River SyphonRetired

Fresno County, California · EIA plant ID 65033 · Operator: orange cove irrigation district
HydroCAISOBA: CISO

×1 MW hydro retired since 2020 (latest Oct 2024)

Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200MWh202220232024

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2022202320242025

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20221.318.7%—
20230.68.0%—
20240.36.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
UNIT1Conventional HydroelectricHY0.30.2Sep 1990Retired Oct 2024—coming soon
UNIT2Conventional HydroelectricHY0.30.2Sep 1990Retired Oct 2024—coming soon
UNIT3Conventional HydroelectricHY0.30.2Sep 1990Retired Oct 2024—coming soon
UNIT4Conventional HydroelectricHY0.40.2Sep 1990Retired Oct 2024—coming soon

Owner / operator

Operator: orange cove irrigation district. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
2081 Terzian Solar Project1 MW10.8 km
Pine Flat165 MW12.7 km
Algonquin Power Sanger LLC62 MW13.3 km
POM Plant 12 MW17.5 km
Reedley Community College Solar3 MW17.7 km
POM Plant 22 MW18 km