OETN1
Obion County, Tennessee · EIA plant ID 64507 · Operator: OE_TN1
Nameplate100MWSummer 108 MW
Generators1in service
Net generation190GWh12 mo to Aug 2026
Capacity factor20%solar units, summer MW
Heat rate—thermal plants only
First online2023
The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2023 | 181.6 | 22.9% | — |
| 2024 | 180.3 | 19.0% | — |
| 2025 | 160.4 | 17.0% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| OETN1 | Solar Photovoltaic | PV | 100 | 108 | Mar 2023 | Operating | — | coming soon |
| OEALD | Solar Photovoltaic | PV | 100 | 100 | planned Dec 2022 | not_current | — | coming soon |
Owner / operator
Operator: OE_TN1. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| OE_TN1 | 100.0% | 100 MW |
Nearby plants
Within 80 km.
| Gleason Generating Facility | 568 MW | 37.5 km |
| Ridgely Energy Farm | 177 MW | 43 km |
| SR Trenton | 2 MW | 49.6 km |
| New Madrid | 1,300 MW | 52.9 km |
| SR Milan | — | 53.3 km |
| SR Trezevant | 7 MW | 54.3 km |