Trojan Solar, LLC
Columbus County, North Carolina · EIA plant ID 64366 · Operator: Sol Systems
Nameplate5MWSummer 5 MW
Generators1in service
Net generation7GWh12 mo to Dec 2025
Capacity factor15%solar units, summer MW
Heat rate—thermal plants only
First online2020
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2020 | 0 | 1.1% | — |
| 2021 | 9.8 | 22.3% | — |
| 2022 | 10.2 | 23.3% | — |
| 2023 | 10.1 | 23.1% | — |
| 2024 | 9.2 | 20.9% | — |
| 2025 | 6.6 | 15.0% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| 30007 | Solar Photovoltaic | PV | 5 | 5 | Dec 2020 | Operating | — | coming soon |
Owner / operator
Operator: Sol Systems. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Sol Systems | 100.0% | 5 MW |
Nearby plants
Within 80 km.
| Delco Farm | 5 MW | 0.8 km |
| Heedeh Solar | 5 MW | 1.6 km |
| International Paper Riegelwood Mill | 84 MW | 4.6 km |
| AGA TAG Solar IV LLC | 5 MW | 13.6 km |
| ATOOD Solar IV, LLC | 5 MW | 13.8 km |
| L V Sutton Combined Cycle | 851 MW | 20.4 km |