Shady Hills Combined Cycle FacilityUnder construction
Pasco County, Florida · EIA plant ID 63802 · Operator: Shady Hills Energy Center, LLC
612 MW under construction (Natural Gas Fired Combined Cycle), first expected Nov 2026 · EIA-860M
Nameplate—MWSummer — MW
Generators0in service · 612 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—
Capacity factor by year
Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| G001 | Natural Gas Fired Combined Cycle | CS | 612 | 538.3 | planned Nov 2026 | Under construction | — | coming soon |
Owner / operator
Operator: Shady Hills Energy Center, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Nearby plants
Within 80 km.
| Shady Hills Generating Station | 541 MW | 0 km |
| Pasco Cnty Solid Waste Resource Recovery | 31 MW | 0.2 km |
| Anclote | 1,112 MW | 30.3 km |
| Mountain View Solar (FL) | 55 MW | 33.3 km |
| Hernando | retired | 34.4 km |
| Lockheed Martin Solar System | 2 MW | 37.6 km |