← Back to map

HernandoRetired

Hernando County, Florida · EIA plant ID 61779 · Operator: Hernando Energy
OtherBA: SEC

×2 MW other retired since 2020 (latest Oct 2025)

Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.51GWh201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%50%100%20182020202220242026

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20171178.6%—
201810.675.6%—
201910.272.8%—
202013.696.5%—
20211392.8%—
202212.589.2%—
20239.768.9%—
20244.733.3%—
202500.0%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
ENG1Landfill GasIC1.61.6Feb 2010Retired Oct 2025—coming soon

Owner / operator

Operator: Hernando Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Rattler Solar Plant75 MW19.6 km
Pasco Cnty Solid Waste Resource Recovery31 MW34.2 km
Shady Hills Combined Cycle Facility—34.4 km
Shady Hills Generating Station541 MW34.4 km
Powerline Energy Storage—35.5 km
Crystal River3,449 MW38.9 km