Gemini Solar Hybrid

Clark County, Nevada · EIA plant ID 63352 · Operator: Gemini Solar
SolarBatteriesSolar PhotovoltaicBA: NEVP
Nameplate1,070MWSummer 1,070 MW
Generators2in service
Net generation2,067GWh12 mo to Aug 2026
Capacity factor35%solar units, summer MW
Heat rate—thermal plants only
First online2024

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200GWh20252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%202420252026202735.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20241,600.832.4%—
20252,181.437.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
ARBE1Solar PhotovoltaicPV690690Mar 2024Operating—coming soon
ARPV1BatteriesBA380380Mar 2024Operating—coming soon

Owner / operator

Operator: Gemini Solar. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Solar Partners XI LLC100.0%1,070 MW

Nearby plants

Within 80 km.
Arrow Canyon Solar Hybrid275 MW3.6 km
Moapa Southern Paiute250 MW7.6 km
Dry Lake Solar Energy Center250 MW8.8 km
Dry Lake East Energy Center—9.1 km
Harry Allen745 MW9.6 km
Playa Solar 1, LLC79 MW11.3 km