EDPR CA Solar Park VI LLC (CA) HybridUnder construction

Fresno County, California · EIA plant ID 62892 · Operator: EDPR CA Solar Park VI LLC
SolarCAISOBA: CISO

241 MW under construction (Batteries, Solar Photovoltaic), first expected Oct 2026 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 241 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
SONR2BatteriesBA4040planned Oct 2026Under construction—coming soon
SONRISolar PhotovoltaicPV201200planned Oct 2026Under construction—coming soon

Owner / operator

Operator: EDPR CA Solar Park VI LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Scarlet II Hybrid350 MW2.4 km
EDPR Scarlet III—3.1 km
Scarlet Solar (CA)240 MW3.4 km
Luna Valley200 MW4.3 km
Great Valley Solar Portfolio Holdings, LLC203 MW4.9 km
RE Tranquillity277 MW5.4 km