← Back to map

Grays Landing L&D Hydroelectric ProjectPlanned

Greene County, Pennsylvania · EIA plant ID 62388 · Operator: Rye Development
HydroPJMBA: PJM

12 MW planned (Conventional Hydroelectric), first expected Jun 2028 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
NA1Conventional HydroelectricHY64.5planned Jun 2028Planned—coming soon
NA2Conventional HydroelectricHY64.5planned Jul 2028Planned—coming soon

Owner / operator

Operator: Rye Development. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Fayette Energy Facility715 MW4 km
Hill Top Energy Center, LLC665 MW7.9 km
Point Marion L&D Hydroelectric Project—10.8 km
Gans Solar14 MW11.1 km
Gans88 MW11.1 km
FirstEnergy Fort Martin Power Station1,152 MW12.6 km