← Back to map

Mustang Two

Kings County, California · EIA plant ID 62015 · Operator: RE Mustang Two LLC
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate150MWSummer 150 MW
Generators2in service
Net generation174GWh12 mo to Aug 2026
Capacity factor13%solar units, summer MW
Heat rate—thermal plants only
First online2020

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02040GWh202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%2020202120222023202420252026202713.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20204219.1%—
2021394.130.0%—
2022359.127.3%—
2023381.429.0%—
2024384.129.1%—
2025396.330.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
M2BARSolar PhotovoltaicPV5050Nov 2020Operating—coming soon
M2WHISolar PhotovoltaicPV100100Nov 2020Operating—coming soon

Owner / operator

Operator: RE Mustang Two LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Idemitsu Renewables100.0%150 MW

Nearby plants

Within 80 km.
RE Mustang LLC175 MW0.8 km
Westside Solar Power PV12 MW1 km
Slate Hybrid440 MW1.1 km
RE Kent South, LLC20 MW1.3 km
Almond20 MW1.3 km
Henrietta D Energy Storage LLC10 MW1.5 km