← Back to map

Seabrook Solar

Beaufort County, South Carolina · EIA plant ID 61701 · Operator: Dominion Energy Inc
SolarSolar PhotovoltaicBA: SCEG
Nameplate73MWSummer 73 MW
Generators1in service
Net generation128GWh12 mo to Aug 2026
Capacity factor20%solar units, summer MW
Heat rate—thermal plants only
First online2019

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
051015GWh2020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20192020202120222023202420252026202720.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20194.58.4%—
202015023.5%—
202115123.8%—
2022134.621.2%—
2023104.216.4%—
202476.912.1%—
202592.614.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Solar PhotovoltaicPV72.572.5Dec 2019Operating—coming soon

Owner / operator

Operator: Dominion Energy Inc. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Dominion Energy Inc100.0%73 MW

Nearby plants

Within 80 km.
Trask East Solar12 MW10.5 km
SCE&G Nimitz CSG8 MW21.4 km
Yemassee Solar10 MW21.7 km
Ridgeland Solar Project10 MW23.3 km
Moffett Solar Project71 MW24.6 km
MCRD Parris Island PV Hybrid17 MW26.5 km