Eagle Point Solar

Jackson County, Oregon · EIA plant ID 61560 · Operator: SunStrong Management
SolarSolar PhotovoltaicBA: PACW
Nameplate10MWSummer 10 MW
Generators1in service
Net generation18GWh12 mo to Dec 2025
Capacity factor20%solar units, summer MW
Heat rate—thermal plants only
First online2017

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
012GWh20182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2018202020222024202620.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201700.0%—
201818.721.5%—
201918.921.8%—
202015.517.8%—
202115.417.8%—
202218.120.9%—
202318.120.8%—
20241820.7%—
202517.520.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PGRD4Solar PhotovoltaicPV9.99.9Dec 2017Operating—coming soon

Owner / operator

Operator: SunStrong Management. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
SunStrong Management100.0%10 MW

Nearby plants

Within 80 km.
Biomass One LP40 MW4.3 km
Dry Creek LFG to Energy Projectretired5.1 km
Antelope Creek2 MW7.5 km
Medford Operation9 MW8 km
Eagle Point3 MW14 km
Blackwell Creek Solar1 MW14.7 km