← Back to map

Canis Major Solar Farm

Hartford County, Connecticut · EIA plant ID 61398 · Operator: LSE Canis Major LLC
SolarSolar PhotovoltaicISONEBA: ISNE
Nameplate2MWSummer 2 MW
Generators1in service
Net generation3GWh12 mo to Dec 2025
Capacity factor19%solar units, summer MW
Heat rate—thermal plants only
First online2016

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300400MWh201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20162018202020222024202619.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201600.0%—
20172.715.6%—
20183.419.1%—
20193.620.4%—
20203.519.9%—
20213.318.8%—
20223.821.4%—
20233.520.1%—
20243.620.3%—
20253.419.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
S1980Solar PhotovoltaicPV22Dec 2016Operating—coming soon

Owner / operator

Operator: LSE Canis Major LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
LSE Canis Major LLC100.0%2 MW

Nearby plants

Within 80 km.
ENGIE 2019 ProjectCo-MA1, LLC5 MW3.6 km
Berkshire Power289 MW4.3 km
Route 57 Solar2 MW5.7 km
CES Agawam Tuckahoe Solar Hybrid6 MW6.5 km
CT Airport Authority Solar One—8.5 km
Agawam Solar2 MW8.6 km