Zero Waste Energy Development Co LLC
Santa Clara County, California · EIA plant ID 60220 · Operator: Zero Waste Energy Development Company LLC
Nameplate2MWSummer 1 MW
Generators2in service
Net generation0GWh12 mo to Dec 2025
Capacity factor2%other units, summer MW
Heat rate—thermal plants only
First online2015
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), other units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2015 | 5.8 | 45.3% | — |
| 2016 | 6 | 42.6% | — |
| 2017 | 7 | 49.6% | — |
| 2018 | 4.4 | 31.7% | — |
| 2019 | 3.9 | 27.7% | — |
| 2020 | 4.2 | 30.0% | — |
| 2021 | 5.5 | 38.9% | — |
| 2022 | 2.1 | 15.3% | — |
| 2023 | 2.3 | 16.3% | — |
| 2024 | 1.8 | 13.0% | — |
| 2025 | 0.2 | 2.1% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| ZWED1 | Other Waste Biomass | IC | 0.8 | 0.6 | Feb 2015 | Operating | — | coming soon |
| ZWED2 | Other Waste Biomass | IC | 0.8 | 0.6 | Feb 2015 | Operating | — | coming soon |
Owner / operator
Operator: Zero Waste Energy Development Company LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Zero Waste Energy Development Company LLC | 100.0% | 2 MW |
Nearby plants
Within 80 km.
| SJ/SC WPCP | 14 MW | 0.6 km |
| AT&T Holger | 1 MW | 1.8 km |
| Los Esteros Critical Energy Center | 306 MW | 2 km |
| BD Biosciences - Milpitas, CA | 1 MW | 2.4 km |
| AmericoldCA - Plainville, CT | 2 MW | 2.4 km |