← Back to map

W H ZimmerRetired

Clermont County, Ohio · EIA plant ID 6019 · Operator: Dynegy W H Zimmer
CoalPJMBA: PJM

×1,426 MW coal retired since 2020 (latest May 2022)

Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—Btu/kWhfossil units, electric fuel, HHV
First online—

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-2000200400600800GWh20012003200520072009201120132015201720192021

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%2005201020152020

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
9,2509,5009,75010,00010,2502005201020152020
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20019,632.384.6%9,622
20029,734.685.5%9,608
20039,214.380.9%9,692
20049,229.480.8%9,730
200510,340.890.8%9,675
20069,587.684.2%9,724
20078,308.573.0%9,797
20089,385.982.2%9,959
20097,268.463.8%9,976
20109,700.485.2%9,870
20116,752.659.3%10,305
20124,780.941.9%10,080
20139,361.779.5%9,742
20147,283.761.9%9,726
20155,93750.4%9,762
20165,452.746.2%9,834
20178,172.670.5%9,852
20188,099.170.9%9,653
20193,549.331.1%9,651
20205,572.948.6%9,538
20214,575.240.0%10,117
20223,04781.1%9,956

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
ST1Conventional Steam CoalST1,425.61,305Mar 1991Retired May 2022—coming soon

Owner / operator

Operator: Dynegy W H Zimmer. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Meldahl Hydroelectric Project105 MW9.7 km
Walter C Beckjord4 MW15.1 km
Nestlewood Solar80 MW19.4 km
Pendleton County LFGTE3 MW21.3 km
Brown County LFGTE Power Station5 MW28.4 km
Walton 1 Solar Facility2 MW31.5 km