Brown County LFGTE Power Station
Brown County, Ohio · EIA plant ID 61145 · Operator: Energy Developments Inc
Nameplate5MWSummer 5 MW
Generators3in service
Net generation26GWh12 mo to Dec 2025
Capacity factor67%other units, summer MW
Heat rate—thermal plants only
First online2017
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), other units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2017 | 15.5 | 67.0% | — |
| 2018 | 26.6 | 67.6% | — |
| 2019 | 28.3 | 71.7% | — |
| 2020 | 27.3 | 69.1% | — |
| 2021 | 26.8 | 68.0% | — |
| 2022 | 24.9 | 63.2% | — |
| 2023 | 27 | 68.4% | — |
| 2024 | 28.2 | 71.3% | — |
| 2025 | 26.4 | 66.9% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| GM01 | Landfill Gas | IC | 1.6 | 1.5 | Jun 2017 | Operating | — | coming soon |
| GM02 | Landfill Gas | IC | 1.6 | 1.5 | Jun 2017 | Operating | — | coming soon |
| GM03 | Landfill Gas | IC | 1.6 | 1.5 | Jun 2017 | Operating | — | coming soon |
Owner / operator
Operator: Energy Developments Inc. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Energy Developments Inc | 100.0% | 5 MW |
Nearby plants
Within 80 km.
| Nestlewood Solar | 80 MW | 10.5 km |
| Hillcrest Solar | 200 MW | 20.2 km |
| New Market Solar | 100 MW | 21.7 km |
| Willowbrook Solar I, LLC | 150 MW | 22.2 km |
| Hecate Energy Highland LLC | 300 MW | 22.5 km |
| H L Spurlock | 1,609 MW | 22.9 km |