← Back to map

SR Hazlehurst

Jeff Davis County, Georgia · EIA plant ID 59535 · Operator: SR Hazlehurst, LLC
SolarSolar PhotovoltaicBA: SOCO
Nameplate20MWSummer 20 MW
Generators1in service
Net generation31GWh12 mo to Dec 2025
Capacity factor17%solar units, summer MW
Heat rate—thermal plants only
First online2015

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
024GWh2016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20162018202020222024202617.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20154.214.3%—
201638.722.0%—
201738.722.1%—
201837.521.4%—
201938.221.8%—
20203821.7%—
202134.919.9%—
202235.120.1%—
202334.819.9%—
202431.818.1%—
202530.517.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
HAZLESolar PhotovoltaicPV2020Nov 2015Operating—coming soon

Owner / operator

Operator: SR Hazlehurst, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
SR Hazlehurst, LLC100.0%20 MW

Nearby plants

Within 80 km.
Hazlehurst II53 MW2.8 km
Hazlehurst III40 MW3.6 km
SR Snipesville II107 MW17.4 km
Snipesville86 MW19.6 km
SR Snipesville III107 MW21.9 km
Baxley25 MW24 km