← Back to map

Anaheim Solar Energy Plant

Orange County, California · EIA plant ID 59416 · Operator: Anaheim Public Utilities
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate2MWSummer 2 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor10%solar units, summer MW
Heat rate—thermal plants only
First online2014

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300400MWh20152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20142016201820202022202420269.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20141.216.2%—
20153.419.3%—
20163.419.3%—
20173.318.8%—
20183.319.0%—
20193.218.2%—
20203.218.4%—
20213.218.2%—
20223.318.8%—
20232.916.6%—
20242.715.6%—
20251.79.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PV1Solar PhotovoltaicPV2.12Aug 2014Operating—coming soon

Owner / operator

Operator: Anaheim Public Utilities. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Anaheim Public Utilities100.0%2 MW

Nearby plants

Within 80 km.
UCI Fuel Cellretired3.2 km
AT&T Anaheim1 MW3.8 km
DESI-1 Battery Energy Storage Facilityretired4.3 km
Barre Peaker50 MW5.9 km
Stanton Energy Reliability Center Hybrid161 MW6.1 km
Stanton Battery Energy Storage69 MW6.4 km