← Back to map

Wellsburg Wind Project

Grundy County, Iowa · EIA plant ID 58886 · Operator: MidAmerican Energy Co
WindOnshore Wind TurbineMISOBA: MISO
Nameplate141MWSummer 139 MW
Generators1in service
Net generation305GWh12 mo to Dec 2025
Capacity factor25%wind units, summer MW
Heat rate—thermal plants only
First online2014

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0204060GWh20152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%201420162018202020222024202625.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201432.130.6%—
2015510.841.4%—
2016503.840.7%—
2017490.339.8%—
2018431.135.5%—
2019403.333.2%—
2020431.834.9%—
202147438.4%—
2022525.743.3%—
2023441.836.4%—
2024468.738.5%—
2025304.825.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
WBWFOnshore Wind TurbineWT140.8138.6Dec 2014Operating—siemens SWT-2.3-108

Owner / operator

Operator: MidAmerican Energy Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
MidAmerican Energy Co100.0%141 MW

Nearby plants

Within 80 km.
Ivester Wind Farm91 MW6.6 km
Grundy Center City Light Plant9 MW16.3 km
Dike City Power Plant2 MW29 km
Vienna Wind Farm150 MW30.1 km
Whispering Willow Wind Farm - East200 MW33.1 km
Leonardo Wind 1 LLC3 MW35 km