← Back to map

Dike City Power Plant

Grundy County, Iowa · EIA plant ID 56194 · Operator: City of Dike
OilPetroleum LiquidsMISOBA: MISO
Nameplate2MWSummer 2 MW
Generators1in service
Net generation0GWh12 mo to Dec 2025
Capacity factor0%gas/coal/oil units, summer MW
Heat rate19,250Btu/kWhfossil units, electric fuel, HHV
First online2005Runs as rarely runs

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-2000200400600MWh20052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%200520102015202020250.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
5,00010,00015,00020,0002005201020152020202519,250 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200500.3%10,290
200600.2%10,323
200700.2%10,387
200800.2%9,871
200900.2%9,903
201000.2%9,839
201100.2%9,806
201200.2%9,839
201300.0%—
201400.2%10,129
20152.915.0%—
201600.0%6,571
201700.0%—
201800.0%9,625
2019-0-0.2%—
20200.10.6%13,092
20210.31.8%9,810
202200.2%12,000
20230.10.3%10,800
20240.10.3%8,900
202500.0%19,250

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Petroleum LiquidsIC2.22Jun 2005Operating—coming soon

Owner / operator

Operator: City of Dike. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
City of Dike100.0%2 MW

Nearby plants

Within 80 km.
Gas Turbine (IA)43 MW13.5 km
Cedar Falls Solar Farm2 MW14 km
University of Northern Iowa8 MW14.9 km
Grundy Center City Light Plant9 MW16.3 km
Streeter Station52 MW16.9 km
Electrifarm264 MW17.1 km