← Back to map

Eclipse Wind Farm

Guthrie County, Iowa · EIA plant ID 57873 · Operator: MidAmerican Energy Co
WindOnshore Wind TurbineMISOBA: MISO
Nameplate207MWSummer 200 MW
Generators1in service
Net generation822GWh12 mo to Aug 2026
Capacity factor47%wind units, summer MW
Heat rate—thermal plants only
First online2012

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
020406080GWh20132014201520162017201820192020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%2012201420162018202020222024202646.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2012246.542.1%—
2013727.341.5%—
2014757.443.2%—
2015740.442.3%—
2016747.542.5%—
201771740.9%—
2018638.936.5%—
2019633.436.1%—
2020676.638.5%—
2021680.938.9%—
2022694.439.6%—
2023754.243.0%—
2024759.243.2%—
202583247.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
EWFOnshore Wind TurbineWT207.1200Sep 2012Operating—siemens SWT-2.3-108

Owner / operator

Operator: MidAmerican Energy Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
MidAmerican Energy Co100.0%207 MW

Nearby plants

Within 80 km.
Anita3 MW14 km
Morning Light Wind Farm111 MW14.4 km
Adair Wind Farm175 MW14.7 km
Heartland Divide Wind Project, LLC104 MW20 km
Exira182 MW20 km
Green Energy Machine2 MW21 km