← Back to map

RV CSU Power LLC

Larimer County, Colorado · EIA plant ID 57141 · Operator: RV CSU Power LLC
SolarSolar PhotovoltaicBA: PSCO
Nameplate2MWSummer 2 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor12%solar units, summer MW
Heat rate—thermal plants only
First online2009

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600MWh200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%201020152020202511.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20090.17.6%—
20103.520.8%—
20113.420.6%—
20123.521.1%—
20133.420.4%—
20142.917.6%—
2015318.0%—
20164.627.6%—
20173.420.1%—
20183.420.4%—
2019318.1%—
2020318.0%—
2021318.1%—
20222.313.8%—
20232.515.1%—
20241.810.5%—
20251.911.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CSU1Solar PhotovoltaicPV1.91.9Dec 2009Operating—coming soon

Owner / operator

Operator: RV CSU Power LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
RV CSU Power LLC100.0%2 MW

Nearby plants

Within 80 km.
RV CSU Power II LLC3 MW0.2 km
Coyote Ridge Community Solar2 MW10.1 km
CBEP Solar 32 MW12.7 km
Pivot Solar 42 LLC—17.8 km
Big Thompson5 MW20 km
SR Skylark B2 MW21.2 km