Nameplate136MWSummer 136 MW
Generators1in service
Net generation379GWh12 mo to Dec 2025
Capacity factor32%wind units, summer MW
Heat rate—thermal plants only
First online2009

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02040GWh20102012201420162018202020222024

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%201020152020202531.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2009202.225.2%—
2010376.531.5%—
201141234.5%—
2012364.630.4%—
2013367.230.8%—
2014387.132.4%—
2015333.627.9%—
2016386.332.3%—
2017339.728.4%—
2018386.232.4%—
2019362.930.4%—
2020422.435.3%—
2021401.333.6%—
2022374.131.3%—
2023329.827.6%—
2024399.733.4%—
202537931.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
WPT1Onshore Wind TurbineWT136.3136.3May 2009Operating—siemens SWT-2.3-93
WPT2Onshore Wind TurbineWT262.2262.2planned Oct 2009not_current—coming soon

Owner / operator

Operator: Washington Wind LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Washington Wind LLC100.0%136 MW

Nearby plants

Within 80 km.
Carriger—6.1 km
Goldendale Generating Station303 MW7.9 km
Linden Wind Energy Project50 MW15.2 km
Windy Flats Wind Project262 MW17.1 km
John Day2,160 MW20.2 km
Goodnoe Hills103 MW24.7 km