← Back to map

Red Oak Power LLC

Middlesex County, New Jersey · EIA plant ID 55239 · Operator: Red Oak Operating Services LLC
Natural gasNatural Gas Fired Combined CyclePJMBA: PJM
Nameplate821MWSummer 776 MW
Generators4in service
Net generation2,915GWh12 mo to Aug 2026
Capacity factor43%gas/coal/oil units, summer MW
Heat rate7,327Btu/kWhfossil units, electric fuel, HHV
First online2002Runs as baseload

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400GWh200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%2005201020152020202542.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
6,0008,00010,000200520102015202020257,327 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2002458.3——
2003522.97.5%10,456
20041,66324.7%7,258
20051,471.721.9%7,420
20061,585.523.6%7,458
20072,521.637.6%7,351
20082,296.834.1%7,505
20093,731.255.6%7,357
20104,401.765.6%7,317
20114,992.774.4%7,281
20125,083.375.6%7,186
20133,831.857.1%7,291
20145,428.480.9%7,203
20155,810.186.6%7,228
20165,955.388.5%7,223
20175,293.678.9%7,199
20184,268.463.6%7,149
20195,092.174.9%7,122
20202,779.540.8%7,208
20212,417.935.6%7,215
20223,137.746.2%7,213
20233,149.746.3%7,225
20243,249.447.7%7,302
20253,448.650.7%7,252

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Natural Gas Fired Combined CycleCT180.2167.3Mar 2002Operating—coming soon
2Natural Gas Fired Combined CycleCT180.2167.3Mar 2002Operating—coming soon
3Natural Gas Fired Combined CycleCT180.2167.3Mar 2002Operating—coming soon
4Natural Gas Fired Combined CycleCA280.5274Apr 2002Operating—coming soon

Owner / operator

Operator: Red Oak Operating Services LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Red Oak Power, LLC100.0%821 MW

Nearby plants

Within 80 km.
Sayreville Cogeneration Facility430 MW1.1 km
Sayreville Solar Project3 MW1.6 km
Parlin Solar LLC1 MW1.9 km
South River 210 MW2.5 km
South River BESS Phase 110 MW2.5 km
Sayreville212 MW3.1 km